Nova Scotia Power Headquarters

Halifax, Nova Scotia

March 7, 2013

Rating System/Standard
LEED v1
Certification Level
Platinum
Building Type
Office

The transformation of a coal-fired power station on the Halifax harbour to a LEED Platinum commercial building employing 600 people makes for a compelling story of environmental, economic and social sustainability. These broad ambitions were reinforced with impressive energy performance, good use of natural light and an innovative envelope upgrade. The project acknowledges its industrial past in the scale and character of the atrium space, and offers public access to the waterfront where none existed before.

The building, known as 1H, is the winner of the Lieutenant Governor’s Award for Excellence in Engineering and was the first building in Atlantic Canada to achieve Platinum certification.

The following case study was originally published in SAB Magazine, and the CaGBC was granted permission to re-publish here, with slight variations. To view more great articles and profiles about Canada’s green buildings, visit SAB’s website now.

A major example of adaptive re-use on Canada’s East Coast

The LEED Platinum certified Nova Scotia Power (NSP) Corporate Headquarters occupies a decommissioned generating plant in a prominent location in downtown Halifax, with significant frontage on the public board-walk that lines the western edge of Halifax Harbour. The project involved the retention and adaptive re-use of the former generating plant for the headquarters of the provincial electrical utility. The facility houses over 600 staff in approximately 14,600 gross square metres.

The project used an innovative construction strategy that involved the reuse of the existing steel structure and exterior concrete cladding where possible, in conjunction with the insertion of floors within the existing volume. Originally designed to support coal bins and turbines, the existing structure and foundations were robust enough to support the new floors.

Having earned LEED Platinum for its efforts, this project provides an excellent example of sustainability and design and construction innovation for the provincial and national building industry.

NSP’s ambitions for the project were broadly based, falling generally into four:

Environmental: It was the desire of NSP, as the provincial power authority, to have a visible demonstration of its commitment to environmental responsibility and show leadership in energy conservation through the adaptive re-use of a former generating station. Elements such as the original steel structure on the interior and chimney bases converted to skylights retain a memory of the original building and its former use.

Economic: Financial analysis demonstrated that renovation of an existing owned building was the optimal solution to meet future space requirements. It provided the lowest life cycle costs when compared to both renting an existing space, and building new corporate office space.

Civic: This redevelopment of an urban brownfield site demonstrates civic responsibility on behalf of the corporation. An example of urban intensification, it minimized incremental costs of infrastructure improvements.

Social: Relocating but retaining employment within the city, the NSP headquarters supports both the economic and social fabric of downtown Halifax. Materials used were sourced from companies in the region whenever possible in order to support the local economy. The original building was a large concrete mass that formed a barrier to the waterfront. A portion of the existing structure was demolished in order to introduce an atrium, which connects the city to the harbour.

The project addresses the utility’s desire to be a more accessible organization engaged with the community that it serves; transparent entries on both the boardwalk and Lower Water Street levels welcome the public into the facility. The building design locates animated uses, such as the conference centre, atrium, and café with outdoor seating area, facing the boardwalk.

Additional project strategies and results

  • The building also represents the first major use of “chilled beam” technology in Atlantic Canada. The system utilizes (low energy sea) water rather than air to transport cooling thereby lowering energy consumption.
  • Additional energy saving strategies included energy recovery on HVAC, variable speed drives, a tight building envelope, and daylight and occupancy sensors for lighting.

Project Performance

  • Energy intensity (building and process energy) = 100kWh/m2/year
  • Energy intensity reduction relative to reference building under MNECB = 48%
  • Lighting power density = 28.3 kWh/m2
  • Lighting power density relative to model building under MNECB = 45%
  • Potable water consumption from municipal sources = 2.625L/occupant/year
  • Potable water reduction relative to reference building = 24%
  • Reclaimed and recycled materials (new construction) by value = 30%
  • Regional materials (800km radius) by value = 28%

The utility hopes that the refurbishments made to this building will sustain it for at least another 50 years of life. CaGBC’s President and CEO Thomas Mueller has called the project “impressive” saying, “When you have a structure [already] in place, to turn it into a platinum building is no small feat.”

No small feat indeed, making this achievement even more inspiring.

LEED SCORE CARD

Certification LevelPlatinum
Rating SystemLEED Canada for New Construction and Major Renovations 1.0
Total Points earned52
Sustainable Sites8 out of 14
Water Efficiency5 out of 5
Energy & Atmosphere15 out of 17
Materials & Resources8 out of 14
Indoor Environmental Quality11 out of 15
Innovation in Operations5 out of 5

More Case Studies

240 Markland Drive

In 2020, 240 Markland Drive, a mid-rise multi-unit residential building (MURB) located in…
July 22, 2024

Humber Cultural Hub

The art of green building The Humber Cultural Hub (HCH) is part of…
April 2, 2024

Waterfront Innovation Centre

Conceived to achieve the highest standards in environmental sustainability, Menkes Developments‘ state-of-the-art Waterfront…
March 18, 2024

Co-operators New Headquarters

The new Co-operators headquarters building located at 101 Cooper Drive, Guelph, aims to…
June 16, 2023